Time
The Residence Hall project was planned for 4 weeks to be completed. The scheduled time line was:
Week 1: Prep work and initial wiring
Prep work includes installation of conduits between floors and into the hallways. Delivery of all hardware to each floor, cable, and other supplies needed.
Week 2: Installation of wall boxes, punch down in each rooms and installation of panduit along the walls.
Week 3: Fiber runs from Miller to each of the halls. Installation of racks in to the utility room.
Week 4: Testing and security of the racks and connection was done.
The time line had to be met because of all the time left until the students arrives back for classes.