Time

        The Residence Hall project was planned for 4 weeks to be completed. The scheduled time line was:

Week 1: Prep work and initial wiring

        Prep work includes installation of conduits between floors and into the hallways. Delivery of all hardware to each floor, cable, and other supplies needed.

Week 2: Installation of wall boxes, punch down in each rooms and installation of panduit along the walls.

Week 3: Fiber runs from Miller to each of the halls. Installation of racks in to the utility room.

Week 4: Testing and security of the racks and connection was done.

        The time line had to be met because of all the time left until the students arrives back for classes.